Appeal 3271077

Public case and site metadata stored from the official casework database, including fields that were empty in the source release.

A clearer next step

See how Inspectors approached issues like yours

Bring your planning decision into a private workspace. We separate the disputed points, then match them with source-located Inspector reasoning from similar appeals.

  • See which issues the decision appears to turn on
  • Compare the facts and open the full appeal records

One private comparison

How the refusal review works

One-off service · No subscription

Similar appeals are evidence to inspect, not a prediction of your outcome.

Official decision document

The decision, section by section

12 sections

Read the development description and the Inspector’s text from the official decision PDF in source order. Source headings are retained where available. Personal and contact details are removed by an automated privacy filter; this is source material, not Rules for You analysis.

Section 01

Development description

demolition of the existing building and redevelopment of the site to provide 307 homes in a series of buildings up to nine storeys, car parking, cycle parking, hard and soft landscaping, and associated facilities.

  1. Section 02

    Preliminary matters

    The Inquiry opened on Monday 5 July and sat for 5 days in virtual format. A preliminary site visit of the surrounding area was carried out on Tuesday 29 June and an accompanied visit to the site and relevant viewpoints was made on Tuesday 13 July. Written closing remarks from the Council and the Finchley Society were received on 9 August 2021 and from the appellant on 13 August. The Inquiry was closed in writing on 20 August 2021.

    The Revised National Planning Policy Framework (NPPF) was issued on 21 July

    The main parties were given the opportunity to incorporate any comments in their closing submissions and these have been taken into account.

  2. Section 03

    Decision

    The appeal is dismissed.

  3. Section 04

    Main issues

    The main issue is the effect of the proposed development on the character and appearance of the area. The Council also refused planning permission on the basis that a S106 Agreement had not been completed covering affordable housing and other matters. A signed and dated S106 [name] (UU) was subsequently submitted which I address later in this decision. A secondary issue which arose during the course of the appeal relates to whether the local planning authority can demonstrate a 5-year supply of housing land, as required by the NPPF.

  4. Section 05

    The site and surroundings

    The site of about 1 hectare comprises a former Homebase store with associated car park. It was built just before the turn of the 21st century on the site of the 1905 [name] tram depot, subsequently a trolley bus and bus garage, which closed in the 1990s. The area around the tram depot was largely built out with terraced and semidetached dwellings before 1936. [name] dwellings line [address] on the north side of the site and streets to the south and west contain mainly semi-detached houses, though [address] has more recent 4 storey flats facing the site at its eastern end. There are also later residential terraced houses in [address] facing the western boundary.

    [name] town centre lies to the north of the site and contains 2 notable and conspicuous tall buildings of 9 storeys ([address], formerly [address], now [address]) and 16 storeys (The Arts Depot, providing a variety of spaces for drama, dance and visual arts as well as residential) grouped around the historic road junction where the A598 [address] diverges from the A1000 [address] ([address]) towards Islington. The 2.5 storey [name] adjoins the site at its north east corner and benefits from planning permission for a substantial extension mainly on the southern side.

  5. Section 06

    Policy background

    The development plan for the area includes the London Plan of 2021 (LonP) and the [name] (CS) and Development Management Policies (DMP) of September 2012. Barnet’s replacement ‘Local Plan Reg 18 [name] was approved for consultation on 6 January 2020. Due to its current stage in the process towards adoption it can only attract limited weight.

    [name] is one of the four priority town centres in the Borough promoted in the CS as a main focus for commercial investment and residential growth. It notes that priority town centres are locations for existing tall buildings which have contributed to their visibility and importance as service centres and places with high levels of public transport accessibility. Development Management Policy DM05 – [name] sets out a criteria-based approach for assessing proposals for tall buildings and Policy CS5 identifies [name] town centre as a potential location where they may be appropriate. CS policy CS6 seeks to promote the town centres whilst ensuring that new development is of an appropriate scale and character for the centre in which it is located.

    The Supplementary Planning Document (SPD) North Finchley Town Centre Framework (TCF) of 2018 provides specific guidance on interpreting and implementing Barnet’s Local Plan policies in supporting the potential for future growth and to manage anticipated change. In conjunction with this, [name] (TBS) of 2010 and its subsequent review and update of 2019 (TBSU) provide advice on where tall buildings (defined as 8-14 storeys) have been developed, where others are planned and the opportunity for new locations to be identified.

  6. Section 07

    Character and appearance

    [name] of 2010 (CSB) is of some age but is a helpful guide to urban character and local distinctiveness. The existing Homebase store is designated as ‘box development’ typology, typically of a large scale with associated car parking and little relationship to surrounding streets. [name] town centre forms a separate typology of older urban fabric with a fine grain. The boundary of the town centre is set out at figure 4 of the TCF and excludes the appeal site and [address] to the north. The residential street primary typology surrounds the appeal site. The town centre boundary is not adjacent, but just touches the appeal site at the north eastern corner where shops at [address] face the adjoining [name].

    The primary residential streets typology is subdivided into secondary typologies. The appellant and the Council are in broad agreement on the characterisation of the surrounding streets as being ‘urban’ rather than ‘suburban’. However the scale of the proposal is such that it would be seen from further away. I agree with objectors that large parts of streets to the south and west of the appeal site ([address] and Way, [address]), designated in the CSB as ‘urban terrace’ mainly consist of semi-detached houses with hipped roofs and generous rear gardens, largely indistinguishable from development on the east side of the [address] (such as [address], [address] and [address]) designated as ‘suburban’ (TCA 1 and TCA 2 in the appellant’s [name], excepting [address]). The dividing line between sub-typologies is necessarily area based and hard to pin down, but the sense of homogeneity that links contemporary development of much of the area west, south and east of the tram depot in the early 20th century is clearly perceivable. Post-war development along the [address] and at the east end of [address] of greater scale (TCA 4 in the townscape study) does not diminish this. Moreover, the character of the area is very much influenced by attractive small scale domestic features and details typical of the ‘suburban’ period such as carved bargeboards, stained glass, oriel and bay windows and ‘tudor’ gables.

    On the other hand, there can be no dispute that terraces in [address] fall in the secondary typology ‘urban terrace’ along with [address] opposite the Mosque and other streets close to the town centre such as [address] and [address]. The upshot of this is that the site lies in an area of broadly homogenous character consistent with mainly low-rise development of domestic scale. Although on the southern edge of the town centre, the 2 tall buildings there do not impact to any extent on the dynamic experience of local occupiers using their gardens and streets, except perhaps where they are directly in the line of sight, such as from north facing rear gardens in [address] (about 16-18 dwellings at most) and in views along the [address] and [address] looking north. Tall urban development in the town centre is clearly visible from the appeal site car park but does not form a significant part of, or contribute in any appreciable way, to the character of the majority of the residential area around the appeal site. As such the surrounding low to mid-rise residential area is sensitive to change.

    In this immediate context, tall buildings as high as 9 storeys would appear starkly out of keeping, the more so on [address] where the 2 central 9 storey blocks C and D would flank a vehicle access and due to the sloping ground, would present as nearer 10 storeys with the lower ground car parking podium level. The visual impact would be only partly relieved by some single aspect maisonettes and the bulk of the scheme would dominate views from the street and from dwellings and gardens opposite (Viewpoint 5). The variation in height of the 5 tallest blocks seen from the [address] and from [address] and the rest of [address] would do little to mitigate for the overall bulk. Moreover, the limited distance between the blocks would mean that anyone walking along [address] would have a curtailed perception of houses and gardens beyond the scheme to the north and limited opportunity to appreciate the relationship between the scheme and the taller buildings at the centre of [name], which would be about 170m away. The lack of visibility of the ‘podium gardens’ from [address] would further add to the development’s stark appearance.

    The visual impact of the scheme is graphically illustrated in the [name] at Figure 5 which, notwithstanding intervening walls and vegetation, indicates the potential effect on the surrounding low-rise environment and the skyline. The scheme would be prominent in views along [address], [address] (Viewpoint 6) and [address] outside the context of the [name] town centre group. The increased prominence of the built form along adjacent streets would not just be local but would be apparent from a wider area.

    [name] 9 of the [name] ([address]), it is apparent that residents on the south side of the road would directly face the highest 9 storey elements of the development and residents on the north side would see these blocks high above over the roofs of those on the south side. In the [name] assessment of this photomontage, in contrast to others, residents are not recorded as receptors, despite their dwellings being within about 22-27m of the [address] closer. The sections submitted late in the Inquiry1 also illustrate the degree of change. The wall of the existing Homebase store is rightly acknowledged as a detractor, but this is at the western end of the road and the replacement 4/5 storey blocks F and G would represent an improvement in townscape terms, at the cost of some loss of winter sunlight for the occupiers of Nos. 34-40.

    [address] is about 29m away from the nearest dwelling in [address] and that is the 5 storey element. The 9 storey part is indirectly viewed from houses but is visible above the roofs from the footway. It does not unduly impact on the fine grain character of [address] but lies in the background. In stark contrast, blocks B, C and D of the appeal scheme would be overbearing and would overwhelm the scale and grain of [address] along most of its length. They would be constantly visible on passing along the road. They would not be seen in the context of the tall buildings in the centre but would represent a fundamental change of character in a completely different direction. The repetitive fenestration of these blocks would make the massing more prominent. Even taking into account the improvement at the western end, the significance of the visual effect would represent a moderate-major level of harm.

    Turning to tall buildings guidance, 7 ‘clusters’ of varying height are identified in the TBSU at pages 38/39 within the historic ‘corridor’ along the [address] passing through the Borough. [name] and Whetstone are 1 [name] 9, CD 9.1 identified as suitable for tall buildings of 8-14 storeys, based on the character of the area, proximity to town centres and public transport accessibility. The appeal scheme would fall within the elliptical line on the plan, but would be visually distinct from the [name] and [address] group at the centre of [name]. The site does not fall within any of the 3 [name] identified in the TCF as suitable for sensitively designed tall buildings and referenced in the TBSU. Additionally, they would be seen as a compact group of parallel slabs with substantial combined bulk, very different from the existing tall buildings. As such they would not respond well to the existing grain of the town centre or be well integrated with the predominantly low to mid-rise pattern in the area.

    LonP policy D3 requires optimisation of site capacity through a design-led approach whilst ‘enhancing local context by delivering buildings and spaces that positively respond to local distinctiveness through their layout, orientation, scale, appearance and shape, with due regard to existing and emerging street hierarchy, building types, forms and proportions’ and responding to ‘the existing character of a place by identifying the special and valued features and characteristics that are unique to the locality and respect, enhance and utilise the heritage assets and architectural features that contribute towards the local character’ amongst other things. These aims are in concert with LP policies and the objectives for good design set out in the National Design Guide (NDG).

    LonP policy D9 on tall buildings sets out criteria to be considered including C (1) ii which notes that ‘mid-range views from the surrounding neighbourhood – particular attention should be paid to the form and proportions of the building. It should make a positive contribution to the local townscape in terms of legibility, proportions and materiality’ and iii: ‘Where the edges of the site are adjacent to buildings of significantly lower height or parks and other open spaces there should be an appropriate transition in scale between the tall building and its surrounding context to protect amenity or privacy’. The LonP further defines optimisation as ‘coordinating the layout of the development with the form and scale of the buildings and the location of the different land uses....’ Paragraph 3.3.7 explains that development should be designed to respond to the special characteristics of the distinctive features of a place which can include: predominant architectural styles and/or building materials; architectural rhythm; distribution of building forms and heights. The proposed development responds poorly to the prevailing scale and grain of the surroundings, overemphasises the contribution made to character by tall buildings in the town centre and underplays the effect of the proposal in terms of height and bulk. Positive impacts of the proposal on the [address] and at the western end of the scheme are seriously undermined by the overpowering visual impact of the higher blocks which would have limited space between them, creating an impression of unredeemed mass, quite out of place in an area of fine grain low to mid-rise residential development.

    The Finchley Society refer to the reduction in daylight and sunlight, particularly in winter, that would be experienced by occupiers of properties in [address], mainly due to the height of blocks B and [name] appellant acknowledges that the effects would exceed the BRE guidelines in some cases but points out that in the context of the appeal site, currently comprising a low-rise retail unit and a large open car park in a brownfield location in an urban area, such consequences are to be expected. The NPPF expects a flexible approach which does not inhibit making efficient use of a site. Whilst the resulting living standards in [address] would not be unacceptable following this line of guidance, they would represent a significant and noticeable deterioration in amenity which would be out of character in any low/mid-rise residential area outside a town centre and would represent a dramatic change here. Furthermore, paragraph 71 of the NDG indicates that proposals for tall buildings require special consideration. It has not been explained why it has not been possible to optimise density whilst at the same time better resolving this environmental impact. The effect on daylight and sunlight on occupiers of south facing houses and gardens adds weight to the suggestion that the scheme would be too high and bulky.

    Turning to separation between the proposed blocks, there are instances where flats would face each other across a distance of less than the minimum standard of 18-21 metres set by the Mayor of London in the 2016 [name]; and in most cases less than the Council’s minimum standard of about 21m. Projecting balconies further reduce the distance between opposing units. Staggering the living areas of flats is no answer to the difficulty of avoiding a direct view into bedrooms, which are habitable rooms. Many flats would be single aspect in practice (I give little weight to the idea that a side window onto an adjacent balcony works to provide a ‘dual aspect’) and many future residents would only have a view of other people’s windows to contemplate, especially from deeper within a unit. There would be a clear perception of overlooking if not an obvious invasion of privacy in some cases, based on the minimum standards in policy guidance. Again, whilst not necessarily unacceptable in adopting a ‘flexible’ approach, the consequences of the balance struck to achieve optimisation would be a demonstrably poor outcome in terms of living conditions and character and appearance.

    The lack of any significant articulation in the fenestration of the highest blocks beyond projecting or recessed balconies (the ‘mansard’ upper level having been omitted in design development) would not help to relieve the unremitting and repetitive appearance of these elements. In contrast, the 4, 5 and 6 storey blocks facing the [address], [address] and [address] would be significantly more sympathetic in scale to the surroundings, helped by gable ends, proportionate detailing of brickwork panels and an active street scene.

    The SPD area extends beyond the town centre boundary ‘in order to facilitate and support the regeneration of the town centre’. The southern and northern gateways are indicated to be important elements in securing the town centre’s future improvement and the southern ‘gateway’ includes the appeal site and residential development in [address]. However the town centre boundary is drawn carefully around the rear of [address], now [address], coinciding with the back gardens in [address], which is where there is a strong sense of character change. The TCF acknowledges this at paragraph 6.29, where scale and massing advice for Key Opportunity Site 3 ([address]) suggests a tiered building decreasing in height towards south and west where there is existing residential. Whilst the TCF identifies potential for public realm and gateway improvements as well as intensification on the edge of the town centre, the site does not fall into any of the [name], locations where tall buildings could be appropriate. Even in the KOS areas, the TCF emphasises the importance of respecting height, scale and surrounding context and the need to transition sensitively. The combination of intensively developed blocks of 4, 5, 6, 8 and 9 storeys with a prominent podium would present a strongly discordant element. It would not integrate well with the existing urban fabric and would not, except in two distinct locations, add to the overall quality or be sympathetic to the character of the area.

    To summarise, the minimal space between flats (at the limit of acceptability according to the Mayor’s 2016 [name] at paragraph 2.3.36) the flexible interpretation of ‘dual aspect’ (essentially a bay window, and still difficult to ventilate naturally) the long internal corridors necessary to achieve the development potential desired, the screening necessary to prevent overlooking between flats and the poor ground level ‘dead’ façade of the higher blocks, comprising mostly bin stores, plant rooms and cycle stores facing the central pedestrian walkway all combine to reinforce the impression of a very high level of density that would be unacceptably out of character.

    The NDG advises that a well-designed place comes about through making the right choices at all levels, including, inter alia, the form and scale of buildings. It says (paraphrasing from paragraph 43) that ‘well-designed new development is integrated into its wider surroundings, physically, socially and visually. It is carefully sited and designed, and is demonstrably based on an understanding of the existing situation, including... patterns of built form, to inform the layout, grain, form and scale; the architecture prevalent in the area, including the local vernacular and other precedents that contribute to local character, to inform the form, scale, appearance, details and materials of new development....’ It has not been shown that the appeal scheme meets these important criteria which support one of the overarching objectives of the NPPF which is to foster well-designed, beautiful and safe places.

    In conclusion, the development would conflict with the townscape and design quality aims of LonP policies D3 and D9, CS policy CS05, and DMP policies DM01 and DM05, as well as emerging polices and relevant guidance in the NPPF and NDG.

  7. Section 08

    Housing land supply

    The LonP requirement over 5 years is 11820 dwellings. The parties are agreed that the overall 5 year requirement is 14321 dwellings, taking into account previous shortfalls and the applicable buffer. The extent of the shortfall in the last plan period between 2016/6 and 2019/20 amounted to 1199 dwellings. The delivery of affordable housing has fallen and is significantly below target2.

    The Council currently claims it can demonstrate a 5 year housing land supply (5YRHLS) of 14888 dwellings, equivalent to 5.2 years supply, a decline from 5.3 years according to the figures presented in evidence at the start of the Inquiry. The difference between 5.2 and 5 years amounts to around 568 new dwellings. The appellant assesses the supply position at 4.06 years at best.

    The NPPF advises at Annex 2 that to be considered deliverable, sites for housing should be available now, offer a suitable location for development now, and be achievable with a realistic prospect that housing will be delivered on the site within five years. I accept that about 12173 dwellings of the Council’s supply benefit from an extant planning permission or prior approval and that these are deliverable within 3 or 5 years, according to the NPPF definition, amounting to about 85% of the requirement. I do not accept, on the balance of probabilities, the appellant’s position that predicted rates of delivery at 2 29% of its strategic target in the last 3 monitoring years (GLA Planning Report GLA/6640/S2 CD7.4) category ‘A’ sites Millbrook Park or the [name], given that they are ongoing apartment projects by major developers, are likely to fall as low as predicted by the appellant, even though these are higher than are typical for developments in neighbouring boroughs. I find the Council’s assessment of 368 dwellings per annum (dpa) on small sites as somewhat optimistic, given the number of completions between 2012 and 2017 falling as low as 221 dpa. Choosing any fixed period carries the risk of distortion, but on balance I find the appellant’s suggestion of a 10 year average to be compelling, given that the average for the last 3 years was 391 dpa and recognition that small sites vary with economic cycles. This results in a deduction of 179 dwellings from the 5YRHLS.

    It was not appropriate to carry out an in-depth site analysis during the Inquiry, which relied on a ‘round-table’ session for this issue and confined the discussion to general principles and typical examples. The parties co-operated in preparing a discreet statement of common ground which together with detailed rebuttal proofs, provided the opportunity for concessions and refinement of the picture.

    The majority of the remaining developments relied on by the Council (2715 units) are challenged by the appellant. Many of these sites only have outline planning permission or are identified in the emerging Local Plan which has just completed consultation and is at ‘Reg 19’ stage and no planning application has yet been made. On some sites, planning permission has lapsed and there can be little certainty in terms deliverability. At Whalebones Park (149 units) for instance, the Council refused permission and an appeal (undefended except on S106 grounds) is in progress. It is unclear that all of the dwellings claimed would be delivered within the plan period.

    Importantly, 3 major sites planned for delivery of around 927 dwellings within the plan period present particular difficulties in terms of clear evidence. The Army Reserve Depot may be promoted by the MoD and on an edge of town centre location but is a Reg 19 site and remains occupied by the MoD. No application for planning permission has been made and it does not clearly meet the criteria for deliverability. At [address] and [address] (north of the appeal site) 334 (or 335) the buildings are currently occupied, or in the case of [address], already converted to residential use under permitted development rights. A development partner has withdrawn due to land ownership issues and the ongoing effects of the pandemic and whilst a new partner is on board, there must be a degree of caution regarding the anticipated level of completions. The appellant also draws attention to Broadway Retail Park where at the time of the Inquiry, no decision had been made on a long-standing application for outline planning permission for 400 homes. The site is currently a functioning retail park and subject to significant objections. Delivery is in any case programmed for towards the end of the plan period. No appreciable reliance can currently be attached to this significant site.

    Of the remaining sites in dispute, I find as follows (numbers refer to Council reference):

    [name]:86 units, application submitted: no restrictions: reasonable prospect.

    [name]: 81 units: delivery ongoing by Barratt: reasonable prospect.

    [name]: 130 units: resolution to grant consent: evidence of delivery: reasonable prospect.

    [address] [name]: 12 units: vacant site, being marketed: no constraints: reasonable prospect.

    [name]: 12 units: vacant: no constraints: reasonable prospect.

    [name]: 25 units: evidence from developer aiming for completion 2023: reasonable prospect.

    [name] substation: 23 units: derelict brownfield site: reasonable prospect.

    [address]: 46 units: evidence from TfL: reasonable within 5 years: temporary occupation by synagogue: reasonable prospect this will come forward. 117,119,121,124. [name]: 189 units: [name] confirm planning applications expected summer 2021: reasonable prospect.

    Woodside Park Station: 95 units: brownfield site: 5 year timeframe realistic: reasonable prospect.

    [name]: 20 dwellings: site owned by developer but no consultation: No certainty of delivery for housing.

    Land adjacent Northway and [name]: 120 units: lapsed planning permission: No further assurances: reasons for lapsed consent uncertain: [address] reputation not a reliable indicator: no firm commitment.

    [address]: 61 units: works commenced under prior approval and permission granted for rear extension: reasonable prospect.

    [address]: 139 units: evidence of immediate application and previous prior approval of conversion of former Council premises: reasonable prospect.

    [address]: 48 units: lapsed prior approval: uncertain reasons: no certainty of delivery.

    Of the above, and adding Whalebones Park, 337 dwellings are considered not to show a reasonable prospect of delivery. Adding these to the 927 dwellings referred to in the previous paragraph 31 above indicates that 1264 units should be removed from the Council’s figure of 14709 units (adjusted above for small sites, paragraph 30) resulting in a supply of 13445 units, equivalent to 93.8% of the requirement or about 4.7 years.

    A degree of uncertainty always attaches to delivery from any development site. However, the difficulties associated with those sites highlighted above indicate that on the balance of probabilities, the Council has not provided clear evidence that there is a realistic prospect of sufficient completions occurring within 5 years in order to meet its 5YRHLS requirement. Its most recent record on completions does not inspire confidence. Whilst the 5YRHLS shortfall is not as serious as the appellant suggests, it remains significant. The appeal proposal represents a appreciable contribution which moreover provides affordable housing where the Council has a particular need.

  8. Section 09

    Other matters

    A S106 UU has been provided with the objectives of providing various benefits including affordable housing and viability review, a Travel Plan, a car club, car free development with associated Traffic Management Order contribution, highway works, a carbon offset payment, measures to mitigate for any effects on TV reception and commitments to use reasonable endeavours to use local labour and suppliers. I consider that the provisions of the S106 are directly related to the proposed development, fairly and reasonably related in scale and kind, and would be necessary to make it acceptable. They meet the tests set out in Paragraph 57 of the NPPF and Regulation 122 of the CIL Regulations (2010). I conclude that the requirements of Regulation 123 and Planning Policy Guidance (PPG) have also been satisfied. [name] otherwise minded to allow the appeal, the S106 would attract significant weight.

    The retail unit ([name]) on the corner of [address] and the [address] is a locally listed (non-statutory) building. The prominent position of this building on a corner indicates that its heritage significance would remain easily appreciated and would not be significantly affected by the appeal proposal.

    I have had regard to the submissions regarding the effect on users of the mosque extension in terms of privacy and the impact in terms of character and appearance. Whilst the mosque extension would be lower and smaller in scale than block A of the proposal, it would remain architecturally distinctive because of its form and purpose. There would be no unacceptable effect on its character and the introduction of higher buildings in this part of the [address] would be appropriate. Windows in the flank wall of nearby blocks would mainly be to kitchens and secondary living room windows and would be far enough away from the mosque to avoid an unacceptable impact on privacy.

  9. Section 10

    Conclusion

    Residential use would be entirely appropriate on this site lying close to a town centre. The gateway to the town centre would be appropriately marked along the [address] with a 6 storey block next to the new mosque extension. The element towards the end of [address] would relate positively to the street scene and would not be unacceptably out of scale in the area. The addition of 307 new dwellings would make a significant contribution to meeting housing need in Barnet including much needed affordable units3 and this attracts very significant weight. The redevelopment for housing for a brownfield site that would enhance the viability and vitality of [name] also attracts weight, though benefit would also occur with a less dense scheme. The new housing would be reasonably well served by public transport and would be close to a town centre and local facilities. Limited weight also attaches to CIL payments, the [name] and construction employment.

    However, the design of the scheme under-estimates the sensitivity to change of the largely homogenous low/mid-rise urban terrace and suburban areas around it. In this respect the site is not comparable to the site referred to in the [name] decision4. The overall degree of change would be medium/high but there would be very high impacts caused by, in particular, the 8 and 9 storey blocks seen from [address] and from Christchurch 3 35% by habitable room 4 APP/T5720/W/20/3250440 Avenue and other places. A high to moderate level of harm would result. The combination of barely acceptable distances between flats facing each other, the need for some privacy screens and obscured glazing, the internal corridors, the lack of effective natural cross-ventilation in many flats, the acknowledgement of appreciable detrimental effects on the amount of daylight and sunlight received by occupiers in [address], and the poor quality of experience for those using the main shared pedestrian access through the site, all support the contention that the scheme is intended firstly to maximise dwelling capacity. Whilst that may often be an appropriate aim, it cannot be justified at the cost of an unacceptable level of harm to the character and appearance of the surrounding area, which would pertain for many years. National and local development plan policy at all levels emphasises the need to respond to a site’s context and to respect local distinctiveness. At the Inquiry, it was suggested that the character of the surrounding residential streets had been taken into account as a constraint but the appellant failed to offer persuasive justification for the approach which led to the solution adopted. In particular, the identified potential for height took insufficient account of the ‘sensitive residential adjacencies’ at [address] and failed to address local concerns on density and height firmly expressed in consultation. The scheme fails overall to provide a form, scale and massing solution that would integrate successfully into its surroundings. Change is inevitable- but the tallest blocks in this scheme would be a step too far.

    It has not been convincingly demonstrated that Barnet has a 5 year supply of housing land. Paragraph 11(d) of the NPPF says that when the policies which are most important for determining the application are out-of-date, permission should be granted unless any adverse impacts of doing so would significantly and demonstrably outweigh the benefits, when assessed against the policies in the NPPF taken as a whole. The significant shortfall in affordable housing completions is also relevant to the overall planning balance. The Government has stated that the design quality of new development is too often mediocre and that systemic change is needed to ensure design and beauty is a core part of the planning process. The NDG and reforms to the NPPF further place emphasis on granting permission for well-designed buildings and refusing it for poor quality schemes. The NPPF advises that it is especially important that where there is a shortage of land, developments make efficient use of land and avoid homes being built at low densities, making optimal use of the potential for sites. It is also necessary to ensure that beautiful and sustainable places are created, and the NPPF notes the importance of area-based character assessments in pursuing this goal. The appeal proposal maximises the potential for densification and in doing so fails to respond appropriately to the Council’s own character assessment or up-to-date guidance in the TCF and the TBSU. The detrimental effect on townscape character of the tallest blocks B, C and D would be so great as to significantly and demonstrably outweigh the benefits the scheme would bring.

    For these reasons, the appeal must be dismissed.

  10. Section 11

    [name]

    National Documents 1.1 NPPF 1.2 PPG 1.3 National Design Guide – October 2019 1.4 DCLG: [name] - [name] 2015

    [name] 2.1 London Plan 2.2 GLA Guidance on [name] – 2018 2.3 [name] – 2018 2.4 Mayor’s Air Quality Strategy – 2010 2.5 [name] - Housing 2016 2.6 [name] – [name] and Construction 2014 2.7 [name] – Character and Context 2014 2.8 [name] – [name] and Viability 2017 2.9 [name] – Play and [name] 2012 2.10 The 2017 London Strategic Housing Market Assessment

    [name] 3.1 [name] 2012 3.2 Lb Barnet Development Management Policies 3.3 Lb Barnet Draft Local Plan (Reg 18) January 2018 3.4 North Finchley Town Centre Framework SPD, February 2018 3.5 Planning Obligations SPD, April 2013 3.6 [name], Employment, Enterprise and Training from Development Through S106, SPD, October 2014 3.7 [name] and Construction, October 2016 3.8 Residential Design Guidance, October 2016 3.9 [name] of London Borough of Barnet, November 2010 3.10 [name], December 2019 3.11 GLA: Character and [name] 2014 3.12 2010 [name] of London Borough of Barnet 3.12 ditto A 3.12 ditto B 3.12 ditto C 3.13 Barnet Draft Local Plan (Reg 19)

    Other 4.1 [name] Assessment Report of [name] 2018 4.2 Tesco New Malden Decision 4.[address] [name] 4.4 Note on [name] 4.5 [name] - Point 2 Surveyors Limited Qualifications and Experience 4.6 [name] on Site Context and use of [name]

  11. Section 12

    Targets

    Appeal Documents 5.1 [name] of Case 5.2 Council Statement of Case 5.3 Finchley Society Statement of Case 5.4 Statement of Common Ground Council Documents 5.5 [name]. [name] 5.6 [name] 5.6a [name] 5.6b [name] 5.6c [name] 5.7 [name]. Gummery 5 [name] 5.7a [name] 5.7b [name]. [name] 5.7c [name]. [name] 5.7d [name]. [name] 5.8 [name]. [name] 5 [name] 5.8a [name] 5 [name] 5.8b [name]. [name] 5.8c [name]. [name] 5.8c Call for [name] - [address] 5.8c Call for [name] - Whalebone Park 08.06.15 5.8c [name] 2012 5.8c Head of [name] 5.8c [name] 5.8c Housing & Growth Committee 14 June 2021 Northway - [name] to Site Disposal 5.8c [address] 19_5403_[name] 5.8c [name] on [name] 18 Local Plan 5.8c [name] Society Documents 5.9 A-Q The Finchley Society Statement of Case: [name] 5.10 [name] 5.10a [name] of Evidence 5.10b Appendices to [name] of Evidence 5.11 [name] 5.11a [name] 5.12 Pullan [site address] [name] 5.12a Pullan [site address] [name] 5.13 Pullan [site address] [name] 5.14 Pullan [site address] [name] 5.15 [site address] Appellant Planning Proof of Evidence 5.15a [site address] Appellant Planning Evidence Appendix 5.15b Appendix 7 Appellant Planning Proof 5.16 [site address] Appellant Summary Planning Proof 5.17 [site address] [name] 5.17a [site address] [name]

    [name] 6.1 [name] [name] and Table 11th May 2021 6.2 [name] 6.3 [name] 2018/19. 6.4 [name] 5yls [name] Cd6.5

    [name] 7.1 Planning Officers Reportto Committee 7.2 Planning Officers Report to Committee Addendum 7.3 [name] 1 Response 7.4 [name] 2 Response 7.5 [name] 28th October 2020 7.6 [name] 2nd October 2010 7.7 Letter from Historic England Dated 25th August 2020 7.8 Email from [name] Dated 26th October 2020

    Core Application Documents 8.1 A-F Design and [name], July 2020: 8.2 A-D Townscape and [name] 2020 8.3 Town Planning Statement, July 2020 8.4 July 2020 [name] 8.5 Transport Assessment July 2020 8.6 A-D Daylight, Sunlight and Overshadowing Assessment July 2020 8.7 Built Heritage Statement July 2020 8.8 A Landscape Design and [name] 2020 8.8 ditto B 8.9 Schedule of Accommodation 8.10 Statement of [name]

    Application Amendment Documents 9.1 A Updated Drawing Pack: 9.1 B 9.1 H 9.1 N 9.1 C 9.1 I 9.1 O 9.1 D 9.1 J 9.1 P 9.1 E 9.1 K 9.1 Q 9.1 F 9.1 L 9.1 R 9.1 G 9.1 M 9.1 S 9.1 T Cd9.1u Note on [name] Cd9.1v E1244d6304 Cd9.1w E1244d6306 9.2 CGI 9.3 [name] 9.4 [name] for Planning Application 9.5 Wind Desktop Assessment Cd9.6 Television Reception Impact Assessment Cd9.6a Television Reception Impact Assessment Map

    S106 [name] 10.1 S106 [name] 10.2 Draft S106 Agreement 10.2 A Location Plan 10.2 B Car Club Plan 10.[address] [name] 10.2 [name]

Planning inspector and document dates

The official casework attribution is grouped under a one-way keyed hash and shown only by its local identifier. Decision-letter dates and page references are extracted by fixed first-page rules and checked against that authoritative record.

  • Appeal Decision

    Extracted decision date · page 1
    30 September 2021Matches the official casework database
    Extracted site visit dates
    13 July 2021 (page 1)

Reference and authority

Official identifiers and the planning authority recorded against this case.

Case reference
3271077
Application reference
20/3823/FUL
Lead case reference
Not recorded
Planning authority
London Borough of Barnet
Planning authority code
E09000003

Casework details

The casework, procedure, development and linking details supplied by the official record.

Casework type
Planning Appeal
Procedure
Inquiry
Development type
Major dwellings
Appeal type reason
1. Refused planning permission
Appeal reason
Refusal
Type detail
Planning Appeals - Full
Jurisdiction
Transferred
Link status
Not Linked

Site and development

Published appeal-site measurements and planning designations, without the withheld precise location fields.

Site area
1.07 hectares
Floor space
27,514 m²
Number of residences
307
Site in Green Belt
No
Agricultural holding
No
Affects setting of a listed building
Not recorded
Historic building grant made
Not recorded
Relates to a conservation area
Not recorded
Flooding is an issue
Not recorded
Site within an AONB
Not recorded
Site within an SSSI
Not recorded

Decision and dates

The published outcome and every imported case date.

Official decision
Dismissed
Decision category
Dismissed
Received date
16 March 2021
Valid date
26 March 2021
Start date
30 March 2021
Planning authority decision date
5 March 2021
Appeal decision date
30 September 2021

Case administration

Published recovery, call-in, costs and enforcement information for this case.

Redetermined
No
Bespoke
No
Date recovered
Not recorded
Date not recovered or derecovered
Not recorded
Call-in date
Not recorded
Costs applied for
Not recorded
Enforcement grounds count
Not recorded
Enforcement grounds
Not recorded

Source and catalogue history

When this record appeared in the rolling official release and when the catalogue stored it.

Source
Planning Inspectorate casework database
Source data system
Horizon
Dataset status
Current release
Catalogue record ID
4032
First seen
20 August 2026 at 14:24
Last seen
20 August 2026 at 16:25
Removed from release
Not recorded
Record created
20 August 2026 at 14:24
Record updated
20 August 2026 at 16:25