Skip to main content
Official casework recordDismissedCurrent release

Appeal 3280424

Public case and site metadata stored from the official casework database, including fields that were empty in the source release.

A clearer next step

See how Inspectors approached issues like yours

Bring your planning decision into a private workspace. We separate the disputed points, then match them with source-located Inspector reasoning from similar appeals.

  • See which issues the decision appears to turn on
  • Compare the facts and open the full appeal records

One private comparison

How the refusal review works

One-off service · No subscription

Similar appeals are evidence to inspect, not a prediction of your outcome.

Official decision document

The decision, section by section

5 sections

Read the development description and the Inspector’s text from the official decision PDF in source order. Source headings are retained where available. Personal and contact details are removed by an automated privacy filter; this is source material, not Rules for You analysis.

Section 01

Development description

the demolition of existing buildings and erection of up to 72 bedroom, predominantly three storey, care home with associated access, parking and landscaping.

  1. Section 02

    Decision

    The appeal is dismissed.

  2. Section 03

    Background and Main Issue

    The condition in dispute relates to a condition on a planning permission granted for the erection of a care home following the demolition of the existing buildings on the site. The condition requires the submission and approval of a drainage strategy for the site prior to the commencement of development.

    The main issue in the appeal is whether the condition is reasonable and necessary to ensure the adequate drainage of the site.

  3. Section 04

    Reasons

    When considering development proposals it is necessary to ensure that adequate drainage is provided for the site. As drainage can affect the layout of the proposal/site and generally needs to be laid out on the site before the main construction of buildings takes place, it is essential that an adequate drainage strategy is agreed with the local planning authority before development commences on the site.

    In this case the appellant has stated that a drainage strategy was submitted in March 2021, several months before the application was determined. As such, he considers that the imposition of this condition was unnecessary.

    As drainage is a technical matter, drainage strategies need to be assessed by various bodies which can include relevant utility companies, the Environment Agency and the Lead Local Flood Authority as well as the Council’s own drainage engineers. The Council have stated that it had not been possible for the submitted drainage strategy to be assessed by the various necessary consultees prior to the application being determined. As a result, they state that it was agreed with the appellant, that rather than delay the decision any further to enable the necessary consultation to take place, the application should be determined with drainage being subject to a pre-commencement

  4. Section 05

    condition.

    I do not know why it had not been possible to consult the necessary consultees before the application was determined but given that this was the case, the local planning authority was not in a position to know whether the submitted drainage strategy would provide a satisfactory drainage solution for the proposal. As such, the condition was necessary and reasonable to ensure that adequate drainage of the site would take place. It therefore meets the test for conditions set out in paragraph 56 of the National Planning Policy Framework.

    The appellant has suggested that the condition should be varied to read that the development takes place in accordance with the drainage strategy that had been submitted in March 2021. However, whether that drainage strategy provides adequate drainage for the site is not something I can determine, as it needs to be consulted on with technical experts with detailed local knowledge of the drainage in the area.

    I therefore consider that the condition is reasonable and necessary to ensure the adequate drainage of the site. Without the condition there is no certainty that the development would provide adequate drainage of the site.

    For the reasons set out above, I conclude the appeal should be dismissed.

Planning inspector and document dates

The official casework attribution is grouped under a one-way keyed hash and shown only by its local identifier. Decision-letter dates and page references are extracted by fixed first-page rules and checked against that authoritative record.

  • Appeal Decision

    Extracted inspector · page 1
    Inspector attribution ID 1128No official casework-database value to compare
    Extracted decision date · page 1
    9 December 2021Matches the official casework database
    Extracted site visit dates
    29 November 2021 (page 1)

Reference and authority

Official identifiers and the planning authority recorded against this case.

Case reference
3280424
Application reference
20/08214/FU
Lead case reference
Not recorded
Planning authority
Leeds City Council
Planning authority code
E08000035

Casework details

The casework, procedure, development and linking details supplied by the official record.

Casework type
Planning Appeal
Procedure
Written Representations
Development type
Other Major Developments
Appeal type reason
4. Grant planning permission for the development subject to conditions to which you object
Appeal reason
Appeal Against Conditions
Type detail
Planning Appeals - Full
Jurisdiction
Transferred
Link status
Not Linked

Site and development

Published appeal-site measurements and planning designations, without the withheld precise location fields.

Site area
0.44 hectares
Floor space
3,578 m²
Number of residences
0
Site in Green Belt
No
Agricultural holding
No
Affects setting of a listed building
Not recorded
Historic building grant made
Not recorded
Relates to a conservation area
Not recorded
Flooding is an issue
Yes
Site within an AONB
Not recorded
Site within an SSSI
Not recorded

Decision and dates

The published outcome and every imported case date.

Official decision
Dismissed
Decision category
Dismissed
Received date
6 August 2021
Valid date
6 August 2021
Start date
13 August 2021
Planning authority decision date
9 July 2021
Appeal decision date
9 December 2021

Case administration

Published recovery, call-in, costs and enforcement information for this case.

Redetermined
No
Bespoke
No
Date recovered
Not recorded
Date not recovered or derecovered
Not recorded
Call-in date
Not recorded
Costs applied for
Not recorded
Enforcement grounds count
Not recorded
Enforcement grounds
Not recorded

Source and catalogue history

When this record appeared in the rolling official release and when the catalogue stored it.

Source
Planning Inspectorate casework database
Source data system
Horizon
Dataset status
Current release
Catalogue record ID
7350
First seen
20 August 2026 at 14:24
Last seen
20 August 2026 at 16:25
Removed from release
Not recorded
Record created
20 August 2026 at 14:24
Record updated
24 August 2026 at 16:21