Skip to main content
Official casework recordAllowedCurrent release

Appeal 3295181

Public case and site metadata stored from the official casework database, including fields that were empty in the source release.

A clearer next step

See how Inspectors approached issues like yours

Bring your planning decision into a private workspace. We separate the disputed points, then match them with source-located Inspector reasoning from similar appeals.

  • See which issues the decision appears to turn on
  • Compare the facts and open the full appeal records

One private comparison

How the refusal review works

One-off service · No subscription

Similar appeals are evidence to inspect, not a prediction of your outcome.

Official decision document

The decision, section by section

6 sections

Read the development description and the Inspector’s text from the official decision PDF in source order. Source headings are retained where available. Personal and contact details are removed by an automated privacy filter; this is source material, not Rules for You analysis.

Section 01

Development description

the erection of a single storey side extension to form kitchen extension, new utility room and wc.

  1. Section 02

    Decision

    The appeal is allowed, and planning permission is granted for the erection of a single storey side extension to form kitchen extension, new utility room and wc at [site address] , Leicester, Leicestershire [postcode] in accordance with the terms of the application Ref 21/00544/FUL, received by the Council on 19 October 2021, subject to the conditions set out in the schedule to this decision.

  2. Section 03

    Procedural matter

    The name of the appellant is given as [name] on the planning appeal form, whereas the name appearing on the application form is [name]. As the right of appeal rests solely with the original applicant, I have proceeded on the basis that [name] is the appellant in this case.

  3. Section 04

    Main issue

    The main issue is the effect of the proposed development on the character and appearance of the local area.

  4. Section 05

    Reasons

    The appeal property is a 2-storey semi-detached dwelling that occupies a prominent corner plot at the junction of [address] and [address] within an estate style residential area. Near to the site, I saw that buildings vary in size, type and design with some properties externally altered and extended. Consequently, there is some variety in the existing built form within the street scene and the local area to which No 50 belongs.

    The proposed side extension would be modest in scale and height, simple in design and set back from the main front wall. As a result, it would clearly be subordinate addition. With materials to match those of the existing dwelling, as proposed, the proposal would relate reasonably well to the host building.

    The finished building would appear more substantial in-built form and so it would gain some prominence in the street scene. The gap between the house and the adjacent highway would also be reduced with the introduction of the new extension. Even so, the completed dwelling would be noticeably set back from [address] with a low eaves level and a mono-pitched roof that would keep a relatively low profile when seen from the road. With adequate space retained around each side of the finished building, the sense of openness around the corner of the adjacent junction would be retained. In those circumstances, the corner plot of No 50 would not feel overly built up nor would the adjacent junction appear or be perceived as overly narrow or too enclosed.

    The proposal would project noticeably beyond of the front building line of the nearest dwelling facing [address], which broadly aligns with the flank wall of the existing appeal dwelling. However, a sizeable gap separates this neighbouring property and No 50 with detached single storey outbuildings in between. Given that visual separation, and the modest presence of the new extension in the streetscape, no visual disharmony would result from the varied build line or to the established pattern of existing development.

    I saw several examples of buildings with side additions on prominent corner plots that project beyond the front build lines of adjacent properties on their return frontages, including those to which the appellant has referred. In some cases, these existing extensions were larger and more evident in their street scene than would be case with the proposal. These examples indicate that the new extension would not be an uncharacteristic addition to the local area.

    The Council’s Residential Development Supplementary Planning Document (SPD) states that side extensions to existing dwellings on corner plots effectively become front extensions and can have a major impact on the appearance of the street scene. Accordingly, the SPD advises that this type of development is deemed unacceptable unless exceptional circumstances dictate otherwise. For the reasons given, such circumstances exist in this case.

    On the main issue, I conclude that the proposed development would not cause significant harm to the character and appearance of the local area. As such, it does not conflict with Policies 1, 6 and 44 of The Borough of Oadby and Wigston Local Plan 2011–2031 or the Council’s SPD. These policies and guidance aim to ensure that new development achieves a high standard of design, respects local character and is sympathetic to and in keeping with their surroundings. It also adheres to the National Planning Policy Framework, which also states that development should be sympathetic to local character.

    In addition to the standard time limit condition, it is necessary to impose a condition that requires the development to be carried out in accordance with the approved plans for certainty. To ensure the satisfactory appearance of the development, a condition is imposed to require that the external materials match those of the existing building.

    For the reasons set out above I conclude that the appeal should be allowed.

  5. Section 06

    Schedule of conditions

    The development hereby permitted shall begin no later than three years from the date of this decision.

    The development hereby permitted shall be carried out in accordance with the following approved plans: [name]/2021/1, the Location Plan, which shows the site edged red (scale 1:1250) and the Site Layout Plan, which illustrates the position of the proposed extension (scale 1:500).

    The materials to be used in the construction of the external surfaces of the development hereby permitted shall match those used in the existing building.

Planning inspector and document dates

The official casework attribution is grouped under a one-way keyed hash and shown only by its local identifier. Decision-letter dates and page references are extracted by fixed first-page rules and checked against that authoritative record.

  • Appeal Decision

    Extracted inspector · page 1
    Inspector attribution ID 287No official casework-database value to compare
    Extracted decision date · page 1
    23 May 2022Matches the official casework database
    Extracted site visit dates
    12 May 2022 (page 1)

Reference and authority

Official identifiers and the planning authority recorded against this case.

Case reference
3295181
Application reference
21/00544/FUL
Lead case reference
Not recorded
Planning authority
Oadby and Wigston Borough Council
Planning authority code
E07000135

Casework details

The casework, procedure, development and linking details supplied by the official record.

Casework type
Householder (HAS)
Procedure
Written Representations
Development type
Householder developments
Appeal type reason
1. Refused planning permission
Appeal reason
Refusal
Type detail
Planning Appeals - Full
Jurisdiction
Transferred
Link status
Not Linked

Site and development

Published appeal-site measurements and planning designations, without the withheld precise location fields.

Site area
Not recorded
Floor space
24 m²
Number of residences
1
Site in Green Belt
No
Agricultural holding
No
Affects setting of a listed building
Not recorded
Historic building grant made
Not recorded
Relates to a conservation area
Not recorded
Flooding is an issue
Not recorded
Site within an AONB
Not recorded
Site within an SSSI
Not recorded

Decision and dates

The published outcome and every imported case date.

Official decision
Allowed
Decision category
Allowed
Received date
20 March 2022
Valid date
20 March 2022
Start date
30 March 2022
Planning authority decision date
25 February 2022
Appeal decision date
23 May 2022

Case administration

Published recovery, call-in, costs and enforcement information for this case.

Redetermined
No
Bespoke
No
Date recovered
Not recorded
Date not recovered or derecovered
Not recorded
Call-in date
Not recorded
Costs applied for
No
Enforcement grounds count
Not recorded
Enforcement grounds
Not recorded

Source and catalogue history

When this record appeared in the rolling official release and when the catalogue stored it.

Source
Planning Inspectorate casework database
Source data system
Horizon
Dataset status
Current release
Catalogue record ID
15586
First seen
20 August 2026 at 14:24
Last seen
20 August 2026 at 16:26
Removed from release
Not recorded
Record created
20 August 2026 at 14:24
Record updated
24 August 2026 at 16:21