Skip to main content
Official casework recordAllowedCurrent release

Appeal 3317562

Public case and site metadata stored from the official casework database, including fields that were empty in the source release.

A clearer next step

See how Inspectors approached issues like yours

Bring your planning decision into a private workspace. We separate the disputed points, then match them with source-located Inspector reasoning from similar appeals.

  • See which issues the decision appears to turn on
  • Compare the facts and open the full appeal records

One private comparison

How the refusal review works

One-off service · No subscription

Similar appeals are evidence to inspect, not a prediction of your outcome.

Official decision document

The decision, section by section

7 sections

Read the development description and the Inspector’s text from the official decision PDF in source order. Source headings are retained where available. Personal and contact details are removed by an automated privacy filter; this is source material, not Rules for You analysis.

Section 01

Development description

described as ‘Side and [name] to [address]’.

  1. Section 02

    Decision

    The appeal is allowed and planning permission is granted for Side and [name] to [address] at [site address] , Gloucestershire [postcode] in accordance with the terms of the application, Ref 22/00973/FUL, dated 2 September 2022, and the plans submitted with it, subject to the following conditions:

    The development hereby permitted shall begin not later than 3 years from the date of this decision.

    The development hereby permitted shall be carried out in accordance with the following approved plans: CWS 967 04, CWS 967 03d, CWS 967 01b.

    The materials to be used in the construction of the external surfaces of the development hereby permitted shall match those used in the existing building.

    The outbuilding accommodation hereby permitted shall not be occupied at any time other than for purposes ancillary to the residential use of the dwelling known as [site address] .

  2. Section 03

    [name]

    The main issues in this case are: • whether the site is a suitable location for the proposed development with particular regard to whether it would amount to the creation of a separate independent dwelling; and • the effect of the proposed development on the character and appearance of the area.

  3. Section 04

    Location

    The appeal property is a substantial detached 2-3 storey dwelling located within the settlement boundary of Gotherington. However, the Council set out that the outbuilding (summer house) located in the rear garden of the property is located outside the boundary, within the open countryside. The appellant does not dispute this.

    The Council has objected to the appeal scheme because of concerns about the creation of a separate dwelling within the open countryside contrary to national and local planning policies on the location of housing. If a new independent dwelling was created then the appeal scheme would conflict with the restrictions on new homes outside settlements and in the countryside included in Policies RES3, RES4 of the Tewkesbury Borough Local Plan 2011-2031 (LP) and Policies GNDP03 and GNDP11 of the Gotherington Neighbourhood Development Plan 2011- 2031 (GNP).

    The existing outbuilding incorporates a lounge/kitchenette area with a separate toilet. The proposal would add a first floor that would increase the amount of accommodation, with the additional floorspace including two first floor bedrooms. It would therefore have all of the facilities for independent living. However, the courts have held that even if accommodation provides facilities for independent day-to-day living, it would not necessarily become a separate planning unit from the main dwelling, and that this would be a matter of fact and degree.

    The outbuilding would not have a separate access to the main dwelling, and is sited immediately to its rear. Even at two storey it would remain subservient to the extensive main house. I acknowledge that the accommodation proposed internally provides such facilities that none would need to be shared with the main house, however, it is also apparent that there is no obvious front door to the building, with access being provided through a large glazed area which faces the rear garden of the main house. In addition, there is no obvious separate access to the outbuilding except through using the access to the main house. As such, there is a clear functional connection between the two buildings.

    Notwithstanding this, the appellants have made it clear that the intention is to use the additional accommodation as ancillary and occasional temporary accommodation for visiting family members, not as a separate dwelling. Furthermore, LP Policy RES10 sets out that ‘where an extension or outbuilding/annexe is capable of being occupied as a separate self-contained residential unit, any planning permission will be subject to a condition restricting its occupation to being ancillary to the main dwelling.’ I note that the Council suggest such a condition, and this would secure the building as ancillary accommodation.

    Consequently, although it would be self-contained, given the scale and physical relationship of the proposed outbuilding to the main dwelling, there is no compelling evidence before me that allowing this appeal and extending the outbuilding would create a new planning unit, or that the outbuilding would be tantamount to a separate dwelling. If the structure is not built or used as proposed, or if there is a material change of use in the future to create a separate dwelling, then a separate grant of planning permission would be required, and the building would be at risk of enforcement action if such permission is not granted.

    For the reasons outlined above I conclude that the development would not amount to the creation of a separate independent dwelling and therefore that the site is a suitable location for the proposed development. There is therefore no conflict with the requirements of [name] RES3 and RES4, and [name] GNDP03 and GNDP11.

  4. Section 05

    Character and Appearance

    LP Policy RES10 sets out that with regards to the erection of domestic outbuildings and annexes, the scale of the proposal should be ‘appropriate to the character and appearance of the existing dwelling and its surrounding area’.

    The existing main property is a large 2-3 storey dwelling set within a large plot. The extended outbuilding would sit comfortably within the substantial garden area of the main property, and whilst a large two storey building, as set out above, when seen in the context of the much larger two-three storey main house and the extensive curtilage of the property, it would remain subordinate and appropriate in scale.

    In the wider context, I note that there is a varied building line in the vicinity, with the appeal property set considerably back from the highway behind No 55. Given its location, the outbuilding would not be visible from the highway, and there are outbuildings sited in a similar rear position away from the roadside. Whilst they are single storey in nature, there are also visible recently constructed large detached two storey dwellings in a similar position to the west. As such, a two storey structure in this position would not result in an unacceptable visual intrusion nor be unduly prominent.

    I conclude therefore that there is no conflict with [name] SD4 and RES10 and GNP Policy GNDP07, which collectively seek to protect of the character and appearance of the surroundings.

  5. Section 06

    Conditions

    A list of suggested conditions has been provided and I have considered these in light of the Planning Practice Guidance (PPG) and the tests set out in the Framework.

    In addition to the standard time limit condition, requiring the development to be carried out in accordance with the approved plans and controlling the external finish of the dwelling, a condition securing the use of the outbuilding as ancillary to the main house is necessary as set out above.

  6. Section 07

    Conclusion

    There are no material considerations that indicate the development should be determined other than in accordance with the development plan. For the reasons given above and having regard to all other matters raised, the appeal is allowed. [planning inspector] INSPECTOR

Planning inspector and document dates

The official casework attribution is grouped under a one-way keyed hash and shown only by its local identifier. Decision-letter dates and page references are extracted by fixed first-page rules and checked against that authoritative record.

  • Appeal Decision

    Extracted inspector · page 1
    Inspector attribution ID 3478No official casework-database value to compare
    Extracted decision date · page 1
    23 June 2023Matches the official casework database
    Extracted site visit dates
    15 May 2023 (page 1)

Reference and authority

Official identifiers and the planning authority recorded against this case.

Case reference
3317562
Application reference
22/00973/FUL
Lead case reference
Not recorded
Planning authority
Tewkesbury Borough Council
Planning authority code
E07000083

Casework details

The casework, procedure, development and linking details supplied by the official record.

Casework type
Householder (HAS)
Procedure
Written Representations
Development type
Householder developments
Appeal type reason
1. Refused planning permission
Appeal reason
Refusal
Type detail
Unknown
Jurisdiction
Transferred
Link status
Not Linked

Site and development

Published appeal-site measurements and planning designations, without the withheld precise location fields.

Site area
Not recorded
Floor space
81 m²
Number of residences
0
Site in Green Belt
No
Agricultural holding
No
Affects setting of a listed building
Not recorded
Historic building grant made
Not recorded
Relates to a conservation area
Not recorded
Flooding is an issue
Not recorded
Site within an AONB
Not recorded
Site within an SSSI
Not recorded

Decision and dates

The published outcome and every imported case date.

Official decision
Allowed
Decision category
Allowed
Received date
28 February 2023
Valid date
28 February 2023
Start date
14 April 2023
Planning authority decision date
22 December 2022
Appeal decision date
23 June 2023

Case administration

Published recovery, call-in, costs and enforcement information for this case.

Redetermined
No
Bespoke
No
Date recovered
Not recorded
Date not recovered or derecovered
Not recorded
Call-in date
Not recorded
Costs applied for
Not recorded
Enforcement grounds count
Not recorded
Enforcement grounds
Not recorded

Source and catalogue history

When this record appeared in the rolling official release and when the catalogue stored it.

Source
Planning Inspectorate casework database
Source data system
Horizon
Dataset status
Current release
Catalogue record ID
34546
First seen
20 August 2026 at 14:24
Last seen
20 August 2026 at 16:27
Removed from release
Not recorded
Record created
20 August 2026 at 14:24
Record updated
24 August 2026 at 16:21