Official casework recordAllowedCurrent release

Appeal 6002066

Public case and site metadata stored from the official casework database, including fields that were empty in the source release.

A clearer next step

See how Inspectors approached issues like yours

Bring your planning decision into a private workspace. We separate the disputed points, then match them with source-located Inspector reasoning from similar appeals.

  • See which issues the decision appears to turn on
  • Compare the facts and open the full appeal records

One private comparison

How the refusal review works

One-off service · No subscription

Similar appeals are evidence to inspect, not a prediction of your outcome.

Official decision document

The decision, section by section

8 sections

Read the development description and the Inspector’s text from the official decision PDF in source order. Source headings are retained where available. Personal and contact details are removed by an automated privacy filter; this is source material, not Rules for You analysis.

Section 01

Development description

described on the application form as “Retrospective application for outbuilding in the rear garden for incidental use as home office/gym”.

  1. Section 02

    Decision

    The appeal is allowed and planning permission is granted for an outbuilding in the rear garden for incidental use as home office/gym at [site address] , Hounslow [postcode] in accordance with the terms of the application, [name]/2025/2507, and subject to the following condition:

    The development hereby permitted is as shown on the approved [name]: L(10)001 (Revision: P02), L(10)010 (Revision: P02) and L(20)100 (Revision: P02).

  2. Section 03

    Preliminary Matters

    I have taken the description of development set out in the banner above from the planning application form. However, in my formal decision, I have deleted the reference to ‘retrospective’ as this does not relate to an act of development.

    The application form states that the development commenced in 2023. On my site visit, I observed that it was substantially complete, with furniture in place and electricity supply connected. Aside from the swap of the gym and home office, what I saw broadly reflected the submitted plans. I have therefore determined the appeal on the basis that the development has already taken place, as did the Council.

    The Council refers to the preparation of the emerging Hounslow Local Plan 2020- 2041 (the emerging Local Plan) which was submitted for examination in June 2025. I have not been provided with a copy of this document. The Council’s reasons for refusal did not cite the emerging Local Plan policies. I note the emerging Local Plan remains at an early stage of preparation. Having regard to paragraph 49 of the National Planning Policy Framework, and mindful of the status of the emerging Local Plan, I have therefore determined the appeal in accordance with the adopted

  3. Section 04

    [name]

    The main issues are the effect of the development on: • the character and appearance of the host dwelling and the surrounding area; and • the living conditions of the neighbouring occupiers, with particular regard to disturbance.

  4. Section 05

    Character and appearance

    The appeal property sits at the end of a terrace and has a side access to the rear garden. The street is predominately residential, with properties of broadly similar style and age many of which have been extended and altered. The appeal property and its neighbours also benefit from typically long rear gardens with various forms of outbuildings within them.

    The outbuilding is sited at the end of a long rear garden. It has a slightly sloped flat roof and an overall height of approximately 2.6m. While taller and further forward than the neighbouring outbuilding at [address], the roof is lower on that side, and the structure is set back from the shared boundaries. It therefore accords with the [name], Sustainability and Design Codes Supplementary Planning Document – Part A5 [name] (2024) (the SPD). Although there is disagreement as to whether its footprint exceeds that of the host dwelling, a reasonable area of usable garden space remains between the house and the outbuilding. Given its height, scale, massing and siting, the development appears subservient to the host dwelling and maintains the established rear-garden character, again complying with the expectations of the SPD.

    Overall, I conclude that the development respects the character and appearance of the host dwelling and the surrounding area. It therefore complies with Policies CC1, CC2 and SC7of the Hounslow Local Plan 2015-2030 (2015) (the LP), which, amongst other matters, seek high-quality development that responds sensitively to its context and preserves local character.

  5. Section 06

    Living conditions

    The outbuilding has a floor space of approximately [address] metres, and is subdivided into a home office, a gymnasium and a shower room. It is not in dispute that a home office and a gym can be uses that are incidental to the enjoyment of the dwelling.

    The SPD expects outbuildings to be used in a manner incidental to the main house and states that proposals involving, or with the potential for, independent residential units will be resisted. It also explicitly states that bathrooms are considered to be primary living accommodation and would not normally be supported.

    The appellant has provided evidence that the outbuilding is used by occupiers of the host dwelling for home working and exercise, with the shower room intended for use after exercising. From my site visit and the submitted plans, the additional floorspace provided is modest in relation to the host dwelling. There is no kitchen or bedroom to support independent living. Although there is a side access to the rear garden, there is no independent access to the outbuilding.

    Having considered its scale and the functional and physical connection with the host dwelling, there is no substantive evidence before me that the outbuilding is, or would become, primary living accommodation or other uses contrary to the SPD. In this context, and as a matter of fact and degree, the presence of a shower room would not facilitate inappropriate or incompatible activities within a private residential garden that would cause unacceptable disturbance to neighbouring occupiers.

    I therefore conclude that the development does not harm the living conditions of the neighbouring occupiers with regard to disturbance. It complies with LP Policy SC7, which, amongst other matters, requires all extensions and alterations of residential properties not to result in harm to the amenity of neighbouring residents.

  6. Section 07

    Conditions

    In imposing conditions, I have had regard to the tests within the National Planning Policy Framework, the Planning Practice Guidance and relevant statute. As the development has already taken place, a condition relating to the time limit for implementation is not necessary. Nevertheless, in the interest of certainty, I have imposed a condition specifying the approved plans for identification purposes.

    In line with LP Policy SC7 and the SPD, the Council has suggested a condition to ensure that the development remains in use solely for a purpose incidental to the enjoyment of the main dwelling. However, this condition would not be necessary as I am satisfied that the description of the development is consistent with the proposal, and there is no proposal before me for a separate dwelling, a bedroom, a kitchen, or any other uses.

  7. Section 08

    Conclusion

    For the reasons given above, the proposal accords with the development plan when read as a whole. Material considerations do not indicate a decision should be taken other than in accordance with the development plan. I therefore conclude that the appeal should be allowed.

Planning inspector and document dates

The official casework attribution is grouped under a one-way keyed hash and shown only by its local identifier. Decision-letter dates and page references are extracted by fixed first-page rules and checked against that authoritative record.

  • Appeal Decision

    Extracted inspector · page 1
    Inspector attribution ID 5356No official casework-database value to compare
    Extracted decision date · page 1
    20 April 2026Matches the official casework database
    Extracted site visit dates
    19 March 2026 (page 1)

Reference and authority

Official identifiers and the planning authority recorded against this case.

Case reference
6002066
Application reference
P/2025/2507
Lead case reference
Not recorded
Planning authority
London Borough of Hounslow
Planning authority code
E09000018

Casework details

The casework, procedure, development and linking details supplied by the official record.

Casework type
Householder (HAS)
Procedure
Written Representations
Development type
Householder developments
Appeal type reason
Not recorded
Appeal reason
refused
Type detail
Householder
Jurisdiction
No Jurisdiction Associated
Link status
Not recorded

Site and development

Published appeal-site measurements and planning designations, without the withheld precise location fields.

Site area
0 hectares
Floor space
290 m²
Number of residences
Not recorded
Site in Green Belt
No
Agricultural holding
Not recorded
Affects setting of a listed building
Yes
Historic building grant made
Not recorded
Relates to a conservation area
Not recorded
Flooding is an issue
Not recorded
Site within an AONB
Not recorded
Site within an SSSI
Not recorded

Decision and dates

The published outcome and every imported case date.

Official decision
Allowed
Decision category
Allowed
Received date
28 November 2025
Valid date
3 December 2025
Start date
8 December 2025
Planning authority decision date
8 October 2025
Appeal decision date
20 April 2026

Case administration

Published recovery, call-in, costs and enforcement information for this case.

Redetermined
Not recorded
Bespoke
Not recorded
Date recovered
Not recorded
Date not recovered or derecovered
Not recorded
Call-in date
Not recorded
Costs applied for
No
Enforcement grounds count
Not recorded
Enforcement grounds
Not recorded

Source and catalogue history

When this record appeared in the rolling official release and when the catalogue stored it.

Source
Planning Inspectorate casework database
Source data system
Back Office
Dataset status
Current release
Catalogue record ID
87594
First seen
20 August 2026 at 14:25
Last seen
20 August 2026 at 16:29
Removed from release
Not recorded
Record created
20 August 2026 at 14:25
Record updated
24 August 2026 at 16:21